IMO und US Coastguard - Zeitplan zur Einführung

Die IMO Regularien betreffen nicht alle Schiffe in gleicher Weise. Die spätesten Daten zum Mitführen von Ballast Water Treatment Systemen variieren nach Größe und Baujahr der Schiffe.

Ballast Water
Capacity (m3)

IMO Timeline for Exchange*
and Treatment

US Coastguard
Phase 1

US Coastguard
Phase 2

existing vessels
1.500 - 5.000

Constructed before 2009
Exchange* or Treatment from
2009 - 2014**
Treatment as of 2014

Constructed before 2012
Treatment from first drydocking
after Jan. 1, 2014

Constructed before 2016
Treatment from first drydocking after
Jan. 1, 2016 or 5 years after BWMS
installation meeting P1 standard

existing vessels
Less 1.500 or
above 5.000

Constructed before 2009
Exchange* of Treatment from
2009 - 2016**
Treatment as of 2016

Constructed before 2012
Treatment from first drydocking
after Jan. 1, 2016

Constructed before 2016
Treatment from first drydocking after
Jan. 1, 2016 or 5 years after BWMS
installation meeting P1 standard

new vessels
less 5.000

Constructed in or after 2009
Treatment on Delivery

Constructed on or after 2012
Treatment on Delivery

Constructed on or after 2016
Treatment on Delivery

new vessels
5.000 or higher

Constructed in or after 2009
but before 2012,
Exchange* or Treatment from
2009 - 2016**
Treatment as of 2016

Constructed on or after 2012
Treatment on Delivery

Constructed on or after 2016
Treatment on Delivery

All new
vessels

Constructed in or after 2012
Treatment on Delivery

Constructed on or after 2012
Treatment on Delivery

Constructed on or after 2016
Treatment on Delivery

* IMO Regularien: Ab 2009 wird von Schiffen der Austausch von Ballastwasser (Exchange) verlangt,
  wenn kein zertifiziertes Ballastwasser Management System an Bord ist.
** Spätestens mit dem nächsten Survey nach dem Jahrestag der Auslieferung eines Schiffes hat
   dieses den Vorschriften zu entsprechen.